Bajel Projects Limited has won a major EPC order valued between ₹200 cr and ₹300 cr from PowerGrid Corporation for a 400kV transmission line. This project aims to enhance renewable energy integration, facilitating the evacuation of 0.25 GW at Davanagere and 2.75 GW at Bellary.
The construction involves approximately 70 kms of transmission line, connecting key substations, which may bolster market sentiment in the power sector.