BHEL wins Gujarat grid order worth up to ₹900 crore
after close1 source ↓machine-written, see hownot a recommendation
- ENGINERSIN close
- ₹299.35
- On the day
- +1.58%
- 52-week high
- ₹321.40
- 52-week low
- ₹163.55
Bharat Heavy Electricals Ltd. received a domestic order worth ₹600 crore to ₹900 crore, excluding goods and services tax, from Power Grid Corporation of India for a renewable-energy integration project in Gujarat. The order was awarded on behalf of a project special purpose vehicle and covers two synchronous condensers at Kalyanpur. ⚡
The equipment will provide reactive-power support to the transmission network as renewable generation expands. Each unit is rated at +300/-200 megavolt ampere reactive (MVAR), helping manage voltage and grid stability around renewable-energy flows. The award broadens Bharat Heavy Electricals’ transmission and grid-equipment presence beyond its core power-generation business.
Order worth ₹600–900 cr is the immediate financial headline. The source headline also cited a ₹2,39,057 cr order book, although the excerpt did not provide the order-book date, composition or project-level breakup. The order therefore adds to the company’s disclosed execution pipeline, while the contract value remains a range rather than a single confirmed amount.
Key points:
• The project is located at Kalyanpur in Gujarat and involves two synchronous condensers.
• Power Grid placed the order for a project SPV connected with renewable-energy transmission.
• The contract excludes GST, so the final billed value will reflect applicable taxation separately.
For the power and infrastructure sectors, the award highlights the equipment required to integrate intermittent renewable generation into the national grid. It also shows how transmission investment is creating opportunities alongside new generation capacity. 🏗️
Unlike the earlier Engineers India earnings bulletin, this is a separate order-led development involving Bharat Heavy Electricals and Power Grid. The next points to watch are the formal order disclosure, execution timeline, commissioning milestones and the contribution of transmission projects to revenue and margins. Any further awards in grid stabilisation or renewable-linked infrastructure will indicate whether this is part of a broader expansion in the company’s non-generation business. 📈
Source: Dalal Street Investment Journal, 11 Nov 2026