NALCO targets 2030 commissioning for Angul smelter expansion
NALCO is targeting December 2030 commissioning for a 500,000 tpy Angul smelter expansion, potentially lifting aluminium capacity from 460,000 tpy to about 1 million tpy. A 1,080 MW captive power project and Pottangi mine ramp-up support the broader plan.
pre-market2 sources ↓machine-written, see hownot a recommendation
- is planned
- 500,000 tpy expansion
National Aluminium Company is targeting December 2030 commissioning for a 500,000 tonnes-per-year brownfield expansion of its Angul aluminium smelter in Odisha. The project would increase the company’s aluminium smelting capacity from 460,000 tpy to approximately 1 million tpy, according to a 13 Nov 2026 release by the Ministry of Mines. The expansion is supported by a technology licensing arrangement with Emirates Global Aluminium. ⚙️
The capacity addition would strengthen domestic aluminium production and increase NALCO’s exposure to the metal’s pricing cycle. A larger smelter base also raises the importance of reliable captive power, with the company planning a 1,080 MW thermal power plant through a 50:50 joint venture with NLC India. The power project is intended to support the expanded smelting operation and reduce exposure to external electricity availability and costs. ⚡
The broader raw-material plan includes operationalising the Pottangi bauxite mines within the next two to three months. The mines are expected to raise bauxite production from approximately 7 million tonnes to more than 10 million tonnes, supporting the company’s upstream supply position as smelting capacity expands. This vertical integration is relevant for margins because bauxite availability is a key input for alumina and aluminium production.
Key points:
- 500,000 tpy expansion is planned at Angul, with commissioning targeted for December 2030.
- Existing aluminium smelting capacity is expected to rise from 460,000 tpy to about 1 million tpy.
- A planned 1,080 MW captive thermal power plant is being developed with NLC India in a 50:50 joint venture.
- Pottangi mine operations are expected within two to three months, with bauxite production projected to exceed 10 million tonnes.
- A separate report said NALCO is also exploring locations for a new 500,000 tpy greenfield smelter, but the site has not been finalised.
For the aluminium sector, the announcement points to a multi-year increase in domestic smelting and raw-material capacity. For the stock, the next observable milestones are the Pottangi mine start-up, formal approvals and progress on the captive power project, followed by construction and commissioning updates for the Angul expansion. The December 2030 target remains a long-dated execution milestone rather than near-term production.
Source: Shanghai Metals Market, 17 Nov 2026