NHPC announces commissioning of Subansiri Lower HE Project unit
pre-market1 source ↓written by the desknot a recommendation
- effective
- 20 Mar 2026
- across three units
- 750 MW
NHPC Limited has declared the Commercial Operation Date (CoD) for Unit #1 (250 MW) of the 2000 MW Subansiri Lower HE Project in Assam/Arunachal Pradesh, effective 20 Mar 2026. This milestone brings the total operational capacity to 750 MW across three units. Further commissioning dates for the remaining units will be announced later.
Not investment advice. For informational purposes only.